The design and California Environmental Quality Act (CEQA) process has been completed. The CEQA process is necessary to identify any possible environmental impacts and actions necessary to mitigate those impacts. The CEQA analysis is conducted in conjunction with the design process of the project. 
 

Project Schedule

 

Feasibility Study                            2013


Measure A Passed                       November 2014


 

Design Phase                                August 2015 to August 2016


DSA / Agency Review Phase        August 2016 to December 2016


Bid / Award Phase                        April 2017


Construction Phase                      April 2017 to January-February 2018

 

Estimated budget: $13,500,000

ground breaking April 27, 2017